hard hatSite Inspection Notification 

Site Inspection Notification

Building Regulations require that the person carrying out building work shall give the Council Notice when the work has reached a particular stage.  These stages are set out below.  Notice may be given in writing, telephone, e-mail, facsimile or in person.

The following are the stages at which notification if applicable must be given.  Stage 6 is not mandatory but is strongly recommended.

1, Commencement - at least 2 working days before work commences
2, Foundation Excavation - at least 1 working day prior to concreting
3, Foundation Concrete - at least 1 working day prior to covering of the concrete
4, Damp Proof Course - at least 1 working day prior to covering of damp proof course
5, Ground Floor Oversite Preparation - at least 1 working day prior to laying of concrete
6, Structural Timber, Steelwork or Concrete - at least 1 working day prior to covering
7, Drains & Private Sewers - at least 1 working day prior to covering
8, Drains after Covering - within 5 working days of covering to enable testing to be carried out
9, Occupation before Completion - not less than 5 working days before occupation
10, Completion - within 5 working days of completion of building works 

In some cases additional inspections may also be considered necessary, if so you will be advised by the Inspecting Surveyor.

Wherever possible inspections of the building works will be carried out the same day providing Notice is received prior to 10.00 am.

If you are in any doubt with regards the above or require additional information or assistance please contact the Building Control Unit direct  023 8068 8327. Email  building.control@eastleigh.gov.uk 
General out of hours emergency number : 023 8068 8191

Back to top

Electronic Forms

Documents

Share on (What's this?):