Crestwood Cycle Route
General Scheme Information
Site record
Works started on site 15th November 2010.
|
Monday
15th Nov 10
|
Woodside Ave
adj bus stop
|
Dry & Sunny
|
Onsite: 4 men
1 Chipper
1 Pickup
1 van
Work has begun on removing the scrub and small trees behind the
existing fence line prior to the fence line being relocated.
_l.JPG)
The existing fence will be relocated 3500mm back from the
existing kerb. Heras fence will be used at any openings to
maintain the security of the school lands.
|
| Thursday 18th Nov 10 |
Woodside Ave opp Bosville |
Dry |
Onsite: 3 men
1 Mini digger
1 dumper
1 pickup
Tree felling complete behind school fence relocation. The
logs have been arranged into brash piles.
_m.JPG)
Digging out and removal to store of acceptable material has
commenced
|
| Friday 19th Nov 10 |
Woodside Ave opp Bosville |
Dry |
Onsite: 3 men
1 Mini digger
1 dumper
1 pickup
Initial removal of bank prior to re-grading
_m.JPG)
Traffic management as per Hampshire County Council
representatives request.
Additional barriers at top of bank to avoid
|
| Wednesday 24th Nov 10 |
Woodside Ave opp Bosville |
Dry |
Onsite: 3 men
1 Mini digger
1 dumper
1 pickup
Bank regraded
_m.JPG)
|
| Monday 29th Nov 10 |
Woodside Ave opp Bosville |
|
Onsite: 3 men
1 Mini digger
1 dumper
1 pickup
First section of path with geotextile and stone
_m.JPG)
|
| Monday 13th Dec 10 |
At Crestwood View
|
|
Onsite: 2 men
1 Mini digger
1 dumper
1 pickup
The existing section of path from the new development is at a
higher level, therefore a second section of kerb has been laid to
raise the level at location
_m.JPG)
entire run from controlled crossing to this point has now
received geotextile and stone
Cable and Wireless cover.
_m.JPG)
C&W are to provide a replacement cover and supervise
installation at the new level. No work can progress on this
cover until 4/1/11 as C&W have a freeze on works to their
apparatus.
|
| 5th Jan 11 |
At Crestwood View |
|
Onsite: 2 men
1 mini digger
1 dumper
1 pickup
1 Roller
Existing access from Crestwood View has required the altering of
the levels to raise up to the path level. Includes a section of
double height kerb.
_m.JPG)
Stoning up of previous section underway.
_m.JPG)
New footway dug out up to Crestwood View development
Lamp column to be relocated by SEC to back of footway
_m.JPG)
Widening of the access into Crestwood College.
This includes the provision of lighting up the curve.
_m.JPG)
|
| 11th Jan 11 |
|
|
Onsite: 6 men
1 mini digger
1 dumper
2 pickups
1 Roller
Works progressed upto Crestwood View
_m.JPG)
Bank regraded, new path has terram and stone
_m.JPG) _m.JPG)
All of new path up to front of Crestwood View edged and stoned
.
Due to levels change a small gulley will be included to avoid
localised ponding in the new path
_m.JPG)
New kerb line in at school entrance to provide width for two way
traffic
_m.JPG)
Revised kerb line at entrance installed to narrow the crossing
width at the College entrance.
_m.JPG)
Works started on new section of fencing to revised line to allow 3
metre path width
_m.JPG)
final tree removed on bank. Agreement with resident
representative to plant ever green to provide mask from road for
property.
|
| 13th Jan 11 |
|
|
Caraway.
Onsite: 3 men
1 mini digger
1 dumper
1 pickups
1 Roller
Queensbury.
2 Men
1 Flat bed hyab
_m.JPG)
New Arun enclosed shelter is delivered too site
_m.JPG)
Fencing at boundary complete
_m.JPG)
New trees planted at Green beside Lydiard Close
|
| 20th Jan 11 |
|
|
Onsite: 3 men
1 mini digger
1 dumper
1 pickups
1 Roller
_m.JPG)
New Privet as screen planted at location of removed tree
_m.JPG) _m.JPG)
New path up to Crestwood View now received binder course. The
lamp columns will be relocated by SEC before final surface course
is layed.
|
| 31st Jan 11 |
|
|
Onsite: 3 men
1 mini digger
1 dumper
1 pickups
1 Roller
_m.JPG)
new path at bus stop dug out and stoned up. Localised
widenning complete with relocation of fence line done. Works
to progress to install block paving to highlight potential conflict
area. Blocks to be permeable design to remove any ponding or
splashing problems for public transport users.
|
| 3rd Feb 11 |
|
|
Onsite: 5 men
1 mini digger
1 dumper
1 pickups
1 Roller
_m.JPG)
Area of path prepared with specific stone types to accept new block
paving at bus stop
_m.JPG)
_m.JPG)
After completion of replacement Daffodil bulb planting new turf
pinned to bank. This should protect the bulbs and reduce time
for establishment of grass to hold bank.
Works also progressing on Shakespeare for connection from
College entrance to new path on Woodside. Section of bank has
been excavated and new slab on edge along bank to be erected 400mm
above proposed footway level.
|
| 9th Feb 11 |
|
|
Onsite: 2 men
1 mini digger
1 dumper
1 pickups
1 Roller

Block paving complete.
Works on new path now up to side gate to College. Edged
and Stoned.
|
| 14th Feb 11 |
|
|
Onsite: 2 men
1 mini digger
1 dumper
1 pickups
1 Roller
_m.JPG)
Final surfacing commenced on sections of new footway
|
| 16th Feb 11 |
|
|
Onsite: 2 men
1 mini digger
1 dumper
1 pickups
1 Roller
_m.JPG)
_m.JPG)
Sections of surfacing complete. At Crestwood View up to area of
banking and from Crestwood View upto the bus shelter.

Area of widenning of existing footway to 3 metres.
|