Page last updated at 09:23 GMT, Thursday, February 17 2011

Crestwood Cycle Route

General Scheme Information

Site record

Works started on site 15th November 2010.

Monday
15th Nov 10

Woodside Ave
adj bus stop

Dry & Sunny

 

Onsite: 4 men

1 Chipper
1 Pickup
1 van

Work has begun on removing the scrub and small trees behind the existing fence line prior to the fence line being relocated.

Scrub Clearance

The existing fence will be relocated 3500mm back from the existing kerb.  Heras fence will be used at any openings to maintain the security of the school lands.

 

Thursday 18th Nov 10 Woodside Ave opp Bosville  Dry Onsite: 3 men

1 Mini digger
1 dumper
1 pickup

Tree felling complete behind school fence relocation.  The logs have been arranged into brash piles.

Brash Pile

Digging out and removal to store of acceptable material has commenced

Friday 19th Nov 10 Woodside Ave opp Bosville Dry

Onsite: 3 men

1 Mini digger
1 dumper
1 pickup

Initial removal of bank prior to re-grading

digging out

Traffic management as per Hampshire County Council representatives request.
Additional barriers at top of bank to avoid

Wednesday 24th Nov 10 Woodside Ave opp Bosville Dry

Onsite: 3 men

1 Mini digger
1 dumper
1 pickup

Bank regraded

Bank regrade

 

Monday 29th Nov 10 Woodside Ave opp Bosville  

Onsite: 3 men

1 Mini digger
1 dumper
1 pickup

First section of path with geotextile and stone

new path

Monday 13th Dec 10

At Crestwood View

 

Onsite: 2 men

1 Mini digger
1 dumper
1 pickup

The existing section of path from the new development is at a higher level, therefore a second section of kerb has been laid to raise the level at location

crestwood view

entire run from controlled crossing to this point has now received geotextile and stone

Cable and Wireless cover.

cable and wireless cover

C&W are to provide a replacement cover and supervise installation at the new level.  No work can progress on this cover until 4/1/11 as C&W have a freeze on works to their apparatus.

5th Jan 11  At Crestwood View  

Onsite: 2 men

1 mini digger
1 dumper
1 pickup
1 Roller

Existing access from Crestwood View has required the altering of the levels to raise up to the path level. Includes a section of double height kerb.

access

Stoning up of previous section underway.

stoning

New footway dug out up to Crestwood View development
Lamp column to be relocated by SEC to back of footway

dig

Widening of the access into Crestwood College.
This includes the provision of lighting up the curve.

school access

11th Jan 11       

Onsite: 6 men

1 mini digger
1 dumper
2 pickups
1 Roller

Works progressed upto Crestwood View

bank
Bank regraded, new path has terram and stone

crestwood viewcrstwood view
All of new path up to front of Crestwood View edged and stoned .
Due to levels change a small gulley will be included to avoid localised ponding in the new path

kerb
New kerb line in at school entrance to provide width for two way traffic

crossing
Revised kerb line at entrance installed to narrow the crossing width at the College entrance.

fence
Works started on new section of fencing to revised line to allow 3 metre path width

tree
final tree removed on bank.  Agreement with resident representative to plant ever green to provide mask from road for property.

13th Jan 11      

Caraway.
Onsite: 3 men
1 mini digger
1 dumper
1 pickups
1 Roller

Queensbury.
2 Men
1 Flat bed hyab

bus shelter
New Arun enclosed shelter is delivered too site

fence
Fencing at boundary complete

trees
New trees planted at Green beside Lydiard Close

20th Jan 11    

Onsite: 3 men
1 mini digger
1 dumper
1 pickups
1 Roller

privet
New Privet as screen planted at location of removed tree

basedbased
New path up to Crestwood View now received binder course.  The lamp columns will be relocated by SEC before final surface course is layed.

31st Jan 11    

Onsite: 3 men
1 mini digger
1 dumper
1 pickups
1 Roller

bus stop
new path at bus stop dug out and stoned up.  Localised widenning complete with relocation of fence line done.  Works to progress to install block paving to highlight potential conflict area.  Blocks to be permeable design to remove any ponding or splashing problems for public transport users.

3rd Feb 11    

 Onsite: 5 men
1 mini digger
1 dumper
1 pickups
1 Roller

bus stop
Area of path prepared with specific stone types to accept new block paving at bus stop 

bank
bank
After completion of replacement Daffodil bulb planting new turf pinned to bank.  This should protect the bulbs and reduce time for establishment of grass to hold bank.

Works also progressing on Shakespeare for connection from College entrance to new path on Woodside.  Section of bank has been excavated and new slab on edge along bank to be erected 400mm above proposed footway level.

9th Feb 11    

Onsite: 2 men
1 mini digger
1 dumper
1 pickups
1 Roller

bus stop SUDS
Block paving complete.

Works on new path now up to side gate to College.  Edged and Stoned.

14th Feb 11    

Onsite: 2 men
1 mini digger
1 dumper
1 pickups
1 Roller

surfacing
Final surfacing commenced on sections of new footway

16th Feb 11    

 Onsite: 2 men
1 mini digger
1 dumper
1 pickups
1 Roller

surface 1  surfacing 2

surfacing 3  surfacing 4

Sections of surfacing complete. At Crestwood View up to area of banking and from Crestwood View upto the bus shelter.

bus stop
Area of widenning of existing footway to 3 metres.

 

 